Upgrading aging heating systems to reduce operating cost

 

Challenge

RSCC, a wire and cable manufacturer, was not operating under efficient conditions due to outdated heating systems. They partnered with Mantis to upgrade the system while not interrupting operations on the production floor.

 

Solution Mix

Mantis designed a solution that reused a significant portion of the system so that operations would not be interrupted. The design also qualified for significant incentive. Mantis managed the total project, installing four new rooftop heaters to replace the existing steam generator and heat exchanger.

 

Results

The new system saves over $50,000 per year and pays back within three years. An additional benefit of this new heating system is the ability to take in 100% cooler outside air at night during the spring, fall, and even summer seasons to precool the building, providing a more comfortable environment during the day.

 

$57,991

TOTAL ANNUAL SAVINGS

$341,277

TOTAL INCENTIVE

174

MT CO2 EQUIVALENT

2.5 Years

PROJECT PAYBACK

Ready to Go?

Have Questions? We’re Here to Help!

Discover more about improving facility performance while reducing costs.

Similar Case Studies

Image
Data center racks
Large‑Scale AI Data Center Developer

Enabling Power-Ready AI Infrastructure at Scale

Read More
Image
university
Leading University in Georgia

Turning reactive roof management into a proactive, data-driven strategy

Read More
Image
chemical manufacturing facility
Multinational Chemical Manufacturer

Organized, data-driven energy procurement strategy unlocks stability and future cost savings

Read More